KUALA LUMPUR, 4 February 2014 – Joint Venture (JV) partners, UEM Construction Sdn Bhd and Bina Puri Sdn Bhd confirmed that they have yet to obtain the Certificate of Completion and Compliance (CCC) for its work package due to an unexpected issue which occurred recently during a follow-up inspection.

The JV partners have discussed and are working with Malaysia Airports Holdings Berhad (MAHB), the authorities, consultants and architects to rectify the matter and rectification work will commence immediately.

“Public safety is the main priority, thus we will ensure proper rectification works are diligently carried out. At the same time, UEMC-Bina Puri JV will work together with MAHB on the next course of action in regard to the issuance of the CCC and the commencement of Operational Readiness and Airport Transfer (ORAT).”